Category:
Wind EnergyClient:
Date:
2011Cost:
Project Summary
Commissioned in 7/2011
Development, Construction, Financing arrangement and operations
19,000 MWh p.a. (p50)
Project Finance: 78%
Turbines: Vestas V90 2MW
Operation and Management activities rendered for first year of operations
Challenges
- …………………………….
- ……………………………..
Solutions
- ………………………………….
- ………….

Racatau – 2.1 MW Hydro Plant
Energy
Galati – 10 MW
Energy
Casimcea – 6 MW
Energy
Curcubata – 15 MW
Energy
Baia III – 12 MW
Energy