Racatau – 2.1 MW Hydro Plant
June 17, 2022

Racatau – 2.1 MW Hydro Plant

Project Summary Development, Construction, Operations Net Capacity Factor: 54% 10,000 MWh p.a. (p50) Francis Turbine Commissioned 11/2013 100% Equity Financed Challenges ……………………………. …………………………….. Solutions …………………………………. ………….

Read More ⟶
Galati – 10 MW
June 17, 2022

Galati – 10 MW

Project Summary Development, Construction, financing arrangement Commissioned 1/2013 31,000 MWh p.a. 35.5% CF (p50) Project Finance: 80% Turbines: Gamesa G90 2MW Challenges ……………………………. …………………………….. Solutions …………………………………. ………….

Read More ⟶
Casimcea – 6 MW
June 17, 2022

Casimcea – 6 MW

Project Summary Commissioned in 7/2011 Development, Construction, Financing arrangement and operations 19,000 MWh p.a. (p50) Project Finance: 78% Turbines: Vestas V90 2MW Operation and Management activities rendered for first...

Read More ⟶
Curcubata – 15 MW
June 17, 2022

Curcubata – 15 MW

Project Summary Commisioned in 06/2016 Construction, Financing, Operation 43,500 MWh p.a.P roject Finance/EU fund Turbines: Vestas V90 3MW   Challenges ……………………………. …………………………….. Solutions …………………………………. ………….

Read More ⟶
Baia III – 12 MW
June 17, 2022

Baia III – 12 MW

Project Summary Commisioned in 06/2011 Development, Construction, Operations Net Capacity Factor: 32% 33,600 MWh p.a. (p50) Project Financed (50%) Turbins: Vestas V90 2MW & Vestas V90 3MW Challenges ……………………………....

Read More ⟶
Baia II – 5 MW
June 17, 2022

Baia II – 5 MW

Project Summary Commisioned in 12/2009 Development, Construction, Operations Net Capacity Factor: 32% 14,000 MWh p.a. (p50) Turbines: Vestas V90 2MW & 3MW Funding: Equity/EU fund Challenges ……………………………. …………………………….. Solutions...

Read More ⟶
Baia I – 2.75 MW
February 2, 2022

Baia I – 2.75 MW

Project Summary Commisioned in 08/2007 First wind park in Romania Net capacity factor: 24% 5,782 MWh p.a. (p50) Turbines: Nordtank/Nordex/HSW Challenges ……………………………. …………………………….. Solutions …………………………………. ………….